GUIDESecurity of Payment Act (Vic), changes from 15 April 2026

The payment rules changed. Most claims didn't.

On 15 April 2026 Victoria's Security of Payment Act changed what subbies can claim, when, and how fast they get paid. Five changes, what to do about them, and a day counter. One page.

Daniel RasmusContract administrator · Quest Communications, Melbourne

Christmas claim calendar: serve by Mon 7 Dec

November claim served Mon 30 Nov (the earliest day)Payment schedule due by Mon 14 Dec
November claim served Mon 7 DecPayment schedule due by Mon 21 Dec
November claim served Tue 8 Dec or laterNot due until Mon 11 Jan or later
December claim (work 1 to 21 Dec), served from 22 DecNot due until about Fri 22 Jan

Why: for the Act, 22 December to 10 January aren't business days, so the 10 business days stop over the break. Your contract can set an earlier date for the schedule. Not legal advice: check your contract.

5 changes that matter.

1

Far more variations can be claimed

The "claimable variations" and "excluded amounts" limits are gone. Variations the head contractor hasn't approved yet, disputed variations, latent conditions and delay costs can now go in a payment claim. Whether they get paid still turns on your contract and your evidence.

Sections 10A and 10B repealed
2

No more reference dates

Claim from the last day of each month you did work (earlier if your contract allows), one claim a month. A claim served early isn't invalid any more. December work from the 1st to the 21st can be claimed from 22 December.

Sections 14A to 14D
3

20 business days, max

A contract term that makes you wait more than 20 business days after your claim to be paid has no effect. If the contract says nothing, it's 10 business days. Pay when paid clauses still don't work.

Sections 12 and 13
4

Read every payment schedule the day it lands

Paying less? They must serve a schedule with reasons within the contract's time or 10 business days, whichever is earlier. A reason they leave out can't be raised later in adjudication. No schedule in time means they owe the full claimed amount.

Sections 15 and 21
5

Time bars can be declared unfair

A notice time bar can be declared unfair if complying wasn't reasonably possible or was unreasonably onerous. It's a safety net for your lawyer, not a plan. Give notice on time, every time.

Section 13A

What to change in your next claim.

Free: a variation register that counts down your notices

Excel. Every variation with its notice deadline counting down (red at 2 days), status, value claimed and approved, and a summary sheet. Victorian public holidays built in.

I may ring you once to ask how it's going. No spam, no list selling. Privacy

Here it is: Variation Register.xlsx. Fill in your company and project at the top, then one row per variation.

Day counter

Pick the date you served the claim. It counts Act business days: no weekends, Victorian public holidays, or 22 Dec to 10 Jan.

Payment schedule due by: pick a date
Latest payment date the contract can set: pick a date
Notice deadline: pick a date

An estimate to plan with, not legal advice. The contract can set an earlier schedule date, and notice periods follow your contract's own wording and its definition of a business day (the notice counter skips weekends and Victorian public holidays only; Melbourne Cup is metro only). Holidays listed to the end of 2027.

Sources, checked 23 Nov 2026: the Act, authorised version 015 · Building and Plumbing Commission · MinterEllison. Claims served before 15 April 2026 stay under the old rules. Anything disputed: talk to your lawyer.